Short answer
- Three layers: epoxy primer, sand-filled intermediate coat and self-leveling topcoat. Mix as specified in the supplied technical data.
- Build 1 mm for workshops and hospitals, 2 mm or more for forklifts.
- Surface dry in 2–4 hours at 15 °C; next layer after 24 hours; foot traffic after 3 days; heavy loads after 15 days.
The three layers and why each matters
Skipping the intermediate coat is the most common way to save money and lose a floor: the topcoat then telegraphs every defect in the slab and is too thin to take wheel loads.
How thick should it be?
| Use | Typical build |
|---|---|
| Offices, storage, light trolleys | 0.3–0.5 mm roller-coat system |
| Workshops, hospitals, schools, showrooms | 1 mm self-leveling |
| Forklifts, warehouses, logistics | 2 mm or more self-leveling |
As a rule of thumb, 1 mm of self-leveling epoxy needs roughly 1.4–1.6 kg per m² (typical; it depends on the filled density of the product). Use our material calculator for a layer-by-layer estimate.
Curing times
| Stage | Time (15 °C, 50% RH) |
|---|---|
| Surface dry | 2–4 hours |
| Next layer | About 24 hours |
| Intermediate coat fully dry | 24–72 hours |
| Foot traffic | 3 days |
| Heavy loads | 15 days |
Five mistakes that ruin self-leveling floors
- Coating damp concrete — above 8% moisture the coating blisters. Test first; use a moisture barrier.
- No mechanical preparation — epoxy does not stick to laitance or oil. Grind or shot-blast.
- Incorrect mixing — weigh and mix as specified in the supplied technical data. Incorrectly mixed epoxy can stay soft or turn brittle.
- Added water — follow the supplied technical data for the intermediate coat.
- Over-rolling with the spiked roller — pull new bubbles in. One pass each way.
Need a specification for a factory, warehouse or hospital floor? Tell us the area, traffic and chemicals.